This project was awarded to PCM Group to replace the corroded sprinkler system under BLB wharf at East Arm port. Project disciplines included fabrication of a new Press fit pipe system of more than 300LM of pipes of different sizes, it is delivered to site and installed in place after removing and safely disposing the old system.
The project included the replacement of water monitor and freshwater flush systems as well, then hydro pressure testing the new system after it’s connected to the main waterline. The use of specially designed barges to access under the wharf providing an innovative, efficient solution to complement our scaffolding team.